Case 01
Replacement of the AE seawater cooling pipes in the engine room
- LocationEngine room
- SystemAuxiliary engine seawater cooling
- DisciplineMarine piping renewal
- ModeOnboard, vessel afloat
Scope of work
- Onboard inspection and assessment of the affected pipe sections.
- Removal of damaged pipe sections and preparation of the work area.
- Supply and installation of replacement seawater cooling pipes.
- Fitting, alignment and connection to the existing system.
- Inspection and testing following installation.
Condition found
- Deterioration and leakage identified within the auxiliary engine seawater cooling pipework.
- Affected piping sections required replacement to maintain system reliability.
Result
- Seawater cooling system restored.
- Reliable auxiliary engine operation supported.